Construction Ro-Ro jetty in record time Britanniëhaven Rotterdam

  • Client Broekman Distriport
  • Contractor Dura Vermeer beton- en waterbouw / Barendrecht
  • Work Ro-Ro jetty Broekman Distriport
  • Date Februari 2015

Dura Vermeer Beton- en Waterbouw has, after an exploratory discussion about the technical solutions and production possibilities of the prefabricated parts of the Ro-Ro jetty, chosen for the expertise and flexible production capacity of Martens as a partner. As a third important party in the construction team, the engineering company Lievense has developed an elaborate the designs.Short communication lines and react quickly were essential to achieve the short construction time. In the form of 14 girders (up to 65 tons), 71 cover slabs and 27 edge beams, around 600 m3 precast concrete was delivered in February 2015 after awarding the contract  at the end of December 2014.